Sprint planning - S105

Sprint planning - S105

@Link to the recording:

 

Themes and priorities for this sprint: 

Highest Core Team Priority

Sensors: https://lite-farm.atlassian.net/browse/LF-4684

(Retired previous epic https://lite-farm.atlassian.net/browse/LF-4491)


Highest Contributor Priorities
*Please tag dev or design on ticket if requirements are not clear or defined

Bugs identified but not fixed for the Animals Release (December, 2024)

Reading for this sprint

Intro reads:

Smart Irrigation specific reads:

Other readings haven’t been significantly updated since S79. However, they’re listed below from most high level to most detailed:

Forward-looking reads:

What’s the definition of done for a story? 

  • Code

  • Note update language requirements:

    • Add string to en

    • Mark your PR with the “new translations” tag

    • The CrowdIn GitHub automations will do the rest

  • Unit testing

  • Check in with @Loic Sans if there’s a visual component to the story

  • Open up a PR, and leave it unassigned. Two reviewers from the core team will be automatically added. Core team to incorporate feedback given during peer review.

  • Passes peer review x 2

    • Reviewer will be auto-added

  • Merged

  • Passes verification

  • User stories with UX/UI component: Passes validation with @Loic Sans

  • Modifications to the

Team availability

S105 runs from … to …

Thursday, January 30th

Wednesday, February 12th

Days in sprint: 10

Person

Days in sprint

Notes

@David Trapp

9

OOO on Monday Feb 3rd; Looking ahead: OOO March

@Sayaka Ono

10

 

@Joyce Sato-Reinhold

10

 

@Duncan Brain

10

 

@Denis Dovganyuk

10

 

@Loic Sans

10

 

@Larisse Cavalcante

10

 

@Divya Chayanam

10

 

@Anto Sgarlatta

10

Looking ahead: OOO 2nd half of Feb

Contributors

 

 

@Gursimran Singh

 

Async