Sprint planning - S54
Themes and priorities for this sprint:
Irrigation task refactor
Soil water potential reading component
Evaluate full stack and senior full stack candidates (opt in)
Pre-reading for this sprint
Relevant pre-readings below. Only read the “still relevant" if you didn’t for S50 - S53.
Updated:
Base object attributes [5 minutes]
Unit displays [20 minutes]
Still relevant:
Irrigation tasks [5 mins] (Take a look at the completion attribute flow)
Task management system [10 mins]
Create a task flows [5 mins]
What’s the definition of done for a story?
Code
Language tags
If EN copy changes on a ticket please set all the non-EN tags to “MISSING”
Es version of the language tag as “MISSING”
Pt version of the language tag as “MISSING”
Fr version of the language tag as “MISSING”
Unit testing
Check-in with Caro if there’s a UI component
Open up to PR and incorporate feedback given during peer review
Passes peer review x 2
Merged
Passes verification
Passes validation
Team availability
S54: Monday, December 12th - Friday, December 23rd
Days in sprint: 9
Community manager: @David Trapp
Person | Days in sprint | Notes |
David | 7.5 days | Travelling half-day on Dec 15, OOO Dec 19 |
Mwaya | 4.5 days | OOO Dec 19 - Jan 3 |
Anant | 9 days |
|
Richard | 9 days |
|
James | Not present |
|
Navdeep | 9 days |
|
Mika | Not present |
|
Orangel | Not present |
|
Caro | 9 days |
|
Duncan | 4.5 days | OOO Dec 19 - Jan 3 |
Kevin | 9 days | Daughter is sick Dec 12 |