Sprint planning - S122

Sprint planning - S122

@Link to the recording:

 https://ubc.zoom.us/rec/share/N7CUbNFkRKkO_Eeh4iBRQJBhjRLgyL098tPy0O-Igx9zG5LQv-Mtuntb2zH-s8y9.BqFGlGLFqTbcu8VA

Passcode: Cpb%5JkZ

 

Themes and priorities for this sprint:

JUST ONE!

  • https://lite-farm.atlassian.net/browse/LF-4951

    • ticket breakdown, architecting, design discussions happened last sprint

    • coding is well underway

    • library feature still needs final decisions from product + UX ← let’s discuss today

 

Not currently a core team priority, but just updating from last sprint:

 

Highest Contributor Priorities:


*Please tag dev or design on ticket if requirements are not clear or defined

Feature Tickets (in progress)

Tech Debt (in progress)

 

Available Tickets

High Priority

 

Medium priority

Lower priority

Reading for this sprint

Intro reads:

Smart Irrigation specific reads:

Other readings haven’t been significantly updated since S79. However, they’re listed below from most high level to most detailed:

Forward-looking reads:

What’s the definition of done for a story? 

  • Code

  • Note update language requirements:

    • Add string to en

    • Mark your PR with the “new translations” tag

    • The CrowdIn GitHub automations will do the rest

  • Unit testing

  • Open up a PR, and leave it unassigned. Two reviewers from the core team will be automatically added. Core team to incorporate feedback given during peer review.

  • Passes peer review x 2

    • Reviewer will be auto-added

  • Merged

  • Passes verification

Team availability

This sprint runs from … to …

Thursday, September 25th

Wednesday, October 8th

Days in sprint: 9 - Holiday TUESDAY Sept 30th (Truth and Reconciliation Day)

Person

Days in sprint

Notes

@Sayaka Ono

9

 

@Joyce Sato-Reinhold

8

OOO Fri Sept 26

@Denis Dovganyuk

9

 

@Divya Chayanam

8

Off Friday Sept 26

@Loic Sans

6

Tue - Thu

@Duncan Brain

3

Back Oct 6, 2025!

 

 

 