Themes and priorities for this sprint:

Celebrate what’s DONE after last Sprint!

 

Design and planning in progress / under discussion:

 

Code in progress:

  • Multi-folk & Multi-day tasks: https://lite-farm.atlassian.net/browse/LF-4924

    • Breakdown + Designs completed last sprint

    • To be put on pause in favour of OFN / soil amendment products / researchers flow (with offline tickets to be picked up while waiting on any of those)

 

Highest Contributor Priorities:


*Please tag dev or design on ticket if requirements are not clear or defined

Feature Tickets

 

Tech Debt (in progress)

Available Bugs

High Priority

 

Medium priority

Lower priority

Reading for this sprint

Intro reads:

Smart Irrigation specific reads:

Other readings haven’t been significantly updated since S79. However, they’re listed below from most high level to most detailed:

Forward-looking reads:

What’s the definition of done for a story? 

  • Code

  • Note update language requirements:

    • Add string to en

    • Mark your PR with the “new translations” tag

    • The CrowdIn GitHub automations will do the rest

  • Unit testing

  • Open up a PR, and leave it unassigned. Two reviewers from the core team will be automatically added. Core team to incorporate feedback given during peer review.

  • Passes peer review x 2

    • Reviewer will be auto-added

  • Merged

  • Passes verification

Team availability

This sprint runs from … to …

Thursday, September 11th

Wednesday, September 24th

Days in sprint: 10

Person

Days in sprint

Notes

@Sayaka Ono

10

 

@Joyce Sato-Reinhold

10

 

@Denis Dovganyuk

10

 

@Divya Chayanam

8

Mon-Thu (off Friday)

@Loic Sans

6

Tue - Thu

 

 

 