Sprint planning - S116

Sprint planning - S116

@Link to the recording:

https://ubc.zoom.us/rec/share/_pwQ_Y8A2ZqhG2pqRJh5SaADM_3bmVGLD7KbhJ82Et-oqrS-_1i1gkjul8YFAxrg.DPb31ZPc_4f4CivR

Passcode: tX7!e6RZ

Themes and priorities for this sprint:

  • Synching up Smart Irrigation (Irrigation Prescriptions) with Ensemble

  • Soil sampling researchers flow

  • Preparing for release 3.8.0

 

Highest Core Team Priorities

Onto preparing for the next release! 3.8.0 and the wrap-up of smart irrigation:

  • Should be able to check farm setups with Lewis / Farming Smarter on MONDAY

  • Ensemble to also be meeting with Lewis this week about pivot properties

  • ESci still to add VRIs… should we schedule a bug bash for the end of this sprint, or is that too optimistic?

 

Follow-ups from last sprint:

  • Release notes?

    • One big set of release notes for 3.7.7 & 3.8.0 (was tagged for Loïc and @Denis Dovganyuk last Sprint) @Divya Chayanam to follow-up and possibly wrap up

  • Translations – Hindi & German coming in?

    • German will be re-contacted; @Divya Chayanam; Divya also to do Hindi

  • Consent

    • @Joyce Sato-Reinhold and @Divya Chayanam to connect about this

    • Update: will not be necessary for this release


Irrigation Prescriptions https://lite-farm.atlassian.net/browse/LF-4759

 

Soil sample researcher’s flow – NOT required for Release 3.8.0 (according to last Sprint Planning’s discussion), but we could look at it while we wait for Ensemble + Smart Irrigation

 

Take a look and discuss this as a backup task:

 

Highest Contributor Priorities
*Please tag dev or design on ticket if requirements are not clear or defined

 

IN PROGRESS (TECH DEBT)

 

AVAILABLE BUGS

High Priority

 

Medium priority

Lower priority

Reading for this sprint

Intro reads:

Smart Irrigation specific reads:

Other readings haven’t been significantly updated since S79. However, they’re listed below from most high level to most detailed:

Forward-looking reads:

What’s the definition of done for a story? 

  • Code

  • Note update language requirements:

    • Add string to en

    • Mark your PR with the “new translations” tag

    • The CrowdIn GitHub automations will do the rest

  • Unit testing

  • Open up a PR, and leave it unassigned. Two reviewers from the core team will be automatically added. Core team to incorporate feedback given during peer review.

  • Passes peer review x 2

    • Reviewer will be auto-added

  • Merged

  • Passes verification

Team availability

S114 runs from … to …

Thursday, July 3rd

Wednesday, July 16th

Days in sprint: 10

Person

Days in sprint

Notes

@Sayaka Ono

10

 

@Joyce Sato-Reinhold

10

 

@Denis Dovganyuk

10

 

@Divya Chayanam

10

 

 

 

 

Contributors