New completion date component for task completion flow - LF-2776Getting issue details... STATUS
Role: N/A
Preferences:
New UI elements have copy displayed in the users preferred language
API: N/A
Dates: N/A
Switching farms:N/A
Input constraints: N/A
Data transformation: N/A
Cascading effects:
Is the user still able to complete a task and are the task completion details correct
Synchronous/ Asynchronous: N/A
External service: N/A
Test Suite
Test Step # | Description | Test Data | Expected Result | Actual Result | Pass/Fail |
1 | While signed on as FW/FO/FM/EO on a farm with atleast one of each type of task planned. The user selects a task, ensures the task is assigned to them and then clicks “mark complete” and then “continue” | User arrives on the complete view, formatted as per Jira ticket | |||
2 | User selects the first radio option for “when was the task completed”, “the original due date”, inputs all other required inputs and completes the task. The user then clicks on the task card for the just completed task | The user is redirected to the read only view for the task. All information is correct including the task completion date | |||
3 | User repeats step 1 and 2 for all the other radio options for “when was the task completed” | ||||
4 | User changes their language preference and repeats step one for each language option | Copy is in the correct language/missing tags exist for the new component | |||
5 | |||||
6 | |||||
7 | |||||
8 | |||||
9 | |||||
10 | |||||
11 | |||||
12 | |||||
13 | |||||
14 |