Themes and priorities for this sprint:
...
Code
Language tags
If En copy changes on a ticket please set all the non-En tags to “MISSING”
Es version of the language tag as “MISSING”
Pt version of the language tag as “MISSING”
Fr version of the language tag as “MISSING”
Unit testing
Check-in with Caro if there’s a UI component
Open up to PR and incorporate feedback given during peer review
Passes peer review x 2
Merged
Passes verification
Passes validation
...
Person | Days in sprint | Notes |
David | ~ 4 days | OOO: Jan 13 & Jan 19 - Wed 25 in Paraguay Delayed responsiveness during this time |
Mwaya | ~ 8.5 days | 1/2 day: Friday, Jan 12 |
Gursimran | 9 days | ~ 4 hours / day Mostly evening Central Time (Edmonton) |
Caro | 9 days | |
Duncan | 6 days | OOO: Monday, Jan 23 Farming otherwise, loosely available |
Craig | 7 days | OOO: Jan 13 and potentially further in the sprint based on interview schedule Jan 19th: Switching ISP, no internet until evening PST. Email is preferred |
Jawad | 9 days | ~ 4 hours per day, 9AM - 1PM PT |
Kevin | ~8 days | OOO: Monday, Jan 23 Potential jury duty Jan 23 - Jan 27 |
Lauren | TBD | Roughly available 12AM - 9AM PT |
...