Background

This retro is for S97S98:

Thursday, September 26thOctober 10th

Wednesday, October 9th23rd

Please add comments before the meeting! We’ll take a few minutes to add additional comments and discuss, then put together action items to operationalize suggestions.

Last sprints (S96S97) retro is here: S96 S97 Retrospective

Info

Discussion topics:

...

Holiday break

  • Previously, we have done 2 weeks. Are we planning to do that again this year?

  • Confirmed: Thurs Dec 19 - Jan 1st (taking exactly one Sprint); return Thurs Jan 2nd

  • Related: support coverage over these two weeks

    • Could be paired with a modification of the automated response… maybe… so email doesn’t have to be checked daily

      • But would need to be translated

      • Several email addresses' responses would need to be adjusted

  • Technical coverage / on call during the break? Have we done this before?

    • We will coordinate phone numbers

Malayalam translations?

...

Still at 83% translated / 70% approved; David Trapp still in communication with + supporting translators daily

  • Can more onboarding material help decrease the follow-up support?

  • Context for more strings

...

Non-latin scripts taking a lot more of Loic Sans's time in In Design

...

  • Can Malayalam run on a different (longer) deadline than the other languages?

...

Team update on language SOP

Start doing

Stop doing

Keep doing

Shout outs

  • Learn what Hollywood square is:

    image-20241009-163530.pngImage Removed
  • Manage roadmap & backlog features in Productboard and link to Jira issues

  • Anto Sgarlatta for doing all the things you do in your short time available it feels like a lot of context switching so bravo!

Action items:

  •  Review previous retro’s action items
  •  

Rollover action items from last time

Rollover action items from last time